National Museum of Archaeology (MUNA)

Key data

Seventy-five thousand (75.000) m2 constructed surface area, the largest museum in Peru and fifth largest in the world.

System implemented

Comprehensive steel construction service: supply, fitting out and industrially reinforced steel reinforcement, and installation of the steel already fitted and/or reinforced “in situ”, of the various structures which made up the work. The execution of the work entailed a workload in which the production rates exceeded 2,500 tonnes per month of reinforced and installed steel, applying a factory industrial pre-assembly system which exceeded 5,000 tonnes of steel and the installation of over 22,000 mechanical connectors.

Project type

Large-scale infrastructures-Special construction.

Location

Lima-Peru

Client

Consorcio MUNA (Consortium)